Article 13 · p.33
JURISDICTIONAL DISPUTES
A mark-up will be held with each Contractor not later than the commencement of the Contractor's work on all Industrial plants or projects and no assignments shall be made before this mark-up. Mark-up assignments shall also apply to all sub-contractors. If a jurisdictional dispute arises once the work has commenced, assignments will be made in accordance with procedures, rules and regulations of the National Joint Board Building Trades Department, A.F.L. & C.I.O., or its successor. The work assignment shall not be completed until a meeting on site has been convened with all Parties involved and until a subsequent meeting (not later than 24 hours) has taken place, at which the Contractor shall present the work assignment on paper to all Parties. The employer shall make available detailed drawings of the work in dispute, subject to any written restrictions the Owner may have.