PART XIV CRANES, HOISTS AND OTHER LIFTING EQUIPMENT — Boom inspection
338
(1) A crane boom used for driving piles with a vibratory hammer shall be inspected in accordance with good engineering practice, and certified safe for continued use by a professional engineer at least every 3 months, and before being returned to lifting service.
338(2)
A crane boom used with a vibratory pile extractor or for dynamic compaction shall be inspected in accordance with good engineering practice, and certified safe for continued use by a professional engineer at least monthly, and before being returned to lifting service.