PART XIV CRANES, HOISTS AND OTHER LIFTING EQUIPMENT — Structural inspection
342
(1) Before erection of a tower crane, the structural components of the crane shall be
342(a)
inspected to determine their integrity by a qualified person using non-destructive testing (NDT) methods meeting the requirements of the Canadian General Standards Board (CGSB); and its structural components shall be inspected to determine their integrity by a qualified person using NDT methods meeting the requirements of the CGSB; and
342(b)
repaired where necessary and those repairs certified by a professional engineer as safe for use. after the inspection required by paragraph (a), the crane, including necessary repairs, shall be certified by a professional engineer as safe for use.
342(2)
Where a tower crane remains erected at a workplace for more than 12 months
342(3)
The inspection and certification of a tower crane scheduled to be dismantled within 15 months of erection may be delayed until before the next erection of the crane.