PART XIV CRANES, HOISTS AND OTHER LIFTING EQUIPMENT — Multiple crane lift
316
(1) A multiple crane lift shall be under the direction of a competent supervisor who shall be responsible for the safe conduct of the operation.
316(2)
A written procedure shall be prepared for a multiple mobile crane lift where the load on a crane exceeds 75% of its rated capacity or where other factors make the lift complex.
316(3)
A written procedure shall be prepared for a lift in which 3 or more cranes are used at one time to hoist a load.
316(4)
Multiple crane lift procedures shall address rigging details, wind speed, hoist line speed, crane travel speed, load distribution and other considerations that may be necessary.
316(5)
The procedures for a multiple crane lift referred to in subsection (2) shall be communicated to all persons involved before hoisting operations are commenced by the supervisor.
316(6)
A means of effective communication shall be established and maintained between all persons involved during a multiple crane lifting operation.